The DM monthly status report covering August activities has been posted to DocuShare, collection-16257. For convenience, the High-level Summary is pasted below. Direct link to the full report: DocuShare Authorization Error
High-level Summary
Community Interactions, Meetings and Workshops
Technical Progress
P1a formal certification now 75%.
The production Alert Production Database (APDB) was deployed with the schema for first alerts. The production Solar System pipeline ran on all Science Validation data taken to date, with a successful roundtrip of upload to the non-public Minor Planet Center “sandbox” server and mirroring the new orbits back to the USDF. Improved artifact rejection and error handling was added to image differencing.
A Profiling document completed for Batch Processing Service tool. Tuning of Kubernetes HTCondor execution at SLAC.
Postgres instances at Summit and Base were updated to version 16.8. This improved replication to USDF. Limited Kubernetes access to users to specific namespaces. This is part of the security plan. Deployed a new backup operator for Kubernetes workloads on summit.