Pre-Operations Broker Integration Exercises

RTN-010 summarizes the project’s current plans for broker integration ahead of LSST commissioning. Comments and questions are welcome. We are presently aiming to begin live connection tests from the USDF in January.

Hi Eric! Do you have any additional information about the dates for these tests? In ALeRCE we have a summer recess during February (although some people in our team will keep working) and we are also moving some operations between servers, so it would be great to know more about this to plan our work this quarter.
Cheers!

We’ve re-prioritized our work slightly due to an internal operations rehearsal in early April, so currently we’re targeting late April for the first interconnection tests from the USDF.