The team continued to make good progress this week towards normal operations activities. We have established reliable power and water at the summit. Fuel and water deliveries look to be stable. Our main fuel tank was topped off at nearly 30,000 liters this week. Supply is possible owing to the improved road conditions. Next week we will begin bringing up facility services. Work to prepare for that went well this week. When facility cooling is available, we will take the first steps to bring the computer room online. Outside, general clearing of snow continued.
View from the summit facility toward Patio 3 where large materials are stored.